Sprint Release Notes
This Page

How to Track OLE Work/Progress

To track the progress of the OLE development during 0.8, the following can be used  to see what is planned, complete specifications, review progress, see new features, understand technical details.

Tool

Link

Description

OLE application

http://demo.ole.kuali.org/ole-demo/portal.jsp

Test Drive past features in OLE 0.6. See DEMO calendar for scheduled outages or FC demo's.

OLE Roadmap

OLE Roadmap

See wiki pages for different planned releases, including OLE 0.8, and refer to linked Scope & Schedule spreadsheet.

F-specs

OLE Spec Writing & Requirements Analysis

Spec Writing tools, inc templates for specs, meetings etc

 

Acceptance Criteria, Test Scripts & Testing

Tips for Acceptance Criteria, Test Scripts

Post Completed Specs

<many links; Use Jira link in Roadmap lists> https://jira.kuali.org/browse/OLE

A story's functional spec should be "linked" to Jira. A story's Codeable spec, when complete and approved, should be attached to Jira as PDF, with jira workflow updated, and email to Patty with spec now available for coding- all handoffs to be scheduled thru Patty. Cc- HTC, SA, BA, SME Team, Tester.

Development Progress

< this wiki >

Find the latest news, release info, technical info

 

OLE Technical Documentation

Scroll to desired spec page to see how we're building a feature

 

OLE Release Documentation - for Milestone 0.8

Review code/features that are promoted to OLE-TEST every other Friday. OLE-TST will be offline during part of day on Friday (see announcements) with code available no later than Monday.

Code/New Features

http://tst.ole.kuali.org/ole-tst/portal.jsp

OLE Application test environment- where to see functions as coded. See Test Promotion Process and sprint schedule below.

 

http://tst.ole.kuali.org/OLE_Rice2/portal.do?selectedTab=main

As above, for Rice 2 (Editors, Circulation, Cataloging)

Testing

https://jira.kuali.org/browse/OLETS

OLE Jira for Test Scripts and Testing status (success, failure) used by OLE Testers.

 

TBA

Wiki page for testers from Rich

Sprint Release Schedule for 0.8

Planned Version #

Sprint Start Date

Sprint End Date
(code promoted)

Details

Latest Handoff DateSpecs

OLE0.8a

4/23/2012

5/4/2012

sprint1toward0.8forHTC

4/13/2012

OLE0.8b

5/7/2012

5/18/2012

sprint2toward0.8forHTC

4/27/2012

OLE0.8c

5/21/2012

6/1/2012

sprint3toward0.8forHTC

5/11/2012

OLE0.8d

6/4/2012

6/15/2012

sprint4toward0.8forHTC

5/25/2012

OLE0.8e

6/18/2012

6/29/2012

sprint5toward0.8forHTC

6/8/2012

OLE0.8f

7/2/2012

7/13/2012

sprint6toward0.8forHTC

6/22/2012

OLE0.8g

7/16/2012

7/27/2012

sprint7toward0.8forHTC

7/6/2012

OLE0.8h

7/30/2012

8/10/2012

sprint8toward0.8forHTC

7/20/2012

OLE0.8i

8/13/2012

8/24/2012

sprint9toward0.8forHTC

8/3/2012

OLE0.8j

8/27/2012

9/7/2012

sprint10toward0.8forHTC

8/17/2012

OLE0.8k

9/10/2012

9/21/2012

All Defect Fixes for OLE 0.8
Work on OLE 1.0


OLE0.8l

9/24/2012

10/5/2012

All Defect Fixes for OLE 0.8
Work on OLE 1.0


OLE0.8m

10/8/2012

10/13/2012

Setting up of Demo (Kuali Days 2012)


Jira Issues: Complete- Release OLE 0.8

The following is an iterative list of completed coding for OLE 0.8. Please see Jira for complete details, or Sprint Release Notes for annotated lists. Below are any coding tickets with status of "closed" for OLE 0.8.

key type summary

Unable to locate Jira server for this macro. It may be due to Application Link configuration.