Project Manager Page

OLE 1.0 Milestone Release Project Plan

Updated 8/29/2013

As we continue the 1.0 QA efforts, details of the project development are listed below.

Summary of efforts:

  • QA efforts are in full force across all modules.
  • The code freeze is occurring in two phases:
    • Describe, Deliver, Select and Acquire were first.  Multiple bugs have already been corrected, testing continue.
    • Systems Integration is a little behind.  Testing is taking place but there are a few items with coding being finalized.
  • Documentation framework has been established, this will allow for online help available from within the application. 
  • Scope for 1.5 is under review with only a few remaining specifications left to complete.