This is a manually synchronised copy of the planning schedule maintained in EBSCO IS Confluence. Details should be current at COP each Wednesday following regular upgrade planning review calls.
MOBIUS is to be upgraded from Poppy-SP-6+ to Quesnelia-SP-4.
Here are the list of actions to be completed:
Activity | Team | Who | Timeline | Status | Notes | |
---|---|---|---|---|---|---|
Test MOBIUS upgrade in a test environment to identify gaps | FSE-Operations | Aliaksei Luhavy | 07/29 - 08/09 | Done | US1291763: MOBIUS: Test Upgrade (part 1) US1271469: MOBIUS: Test Upgrade (part 2) | |
Analyze gaps from FOLIO Hosting | FSE-Operations | Aliaksei Luhavy | 07/29 - 08/09 | Done | ||
Upgrade umsystem-test to Quesnelia-SP-2 | FSE-Operations | Hleb Surnovich | By 08/22/2024 | Done | ||
Come up with a test plan for LOCATE testing | Dreamliner | Tim Auger/Steve Ellis | by 08/26/2024 | Done | Test Plan on Test Rail - Vijay to share link | |
Come up with a test plan for DCB testing | K-Int | Jag/Marc Johnson | by 08/26/2024 | Done | Test Plan on Wiki - Jag to share link to Wiki - FOLIO Upgrade Testing - | |
Test compatibility of DCB against Q umsystem-test on mobius-staging with everything else on Poppy | Tim Auger/K-Int | by 08/30/2024 | Done | |||
Q-SP-3 to be released on August 26th | N/A | |||||
Upgrade intcon to Q-SP-3(FOLIO) | FSE-Operations | 09/02 - 09/06 | Done | US1301786 IT-201
| ||
Create FOLIO MOBIUS dryrun | FSE-Operations | 09/09 - 09/13 | Done and Delivered | |||
MOBIUS Testing Dryrun | MCO | Optimistic: 1 week for dry run Pessimistic: 2-3 weeks 09/16 - 10/04 | Till October 4th | Process for testing dry run and who will participate in testing? | ||
Upgrade intcon to Q-SP-4 | 09/24 - 09/25 | Done | https://folio-org.atlassian.net/issues/?filter=12899 | |||
Blocking Issues Fixes | Tim Auger | Tim Auger | by 09/27 | Done | https://folio-org.atlassian.net/browse/MODDCB-126 is a blocker - part of Q-SP-5 https://folio-org.atlassian.net/browse/MODDCB-130 - part of Q-SP-5 https://folio-org.atlassian.net/browse/MODRTAC-112 is a blocker - being addressed as part of Q-SP-5 - has it been back ported to Q Radhakrishnan Gopalakrishnan | Tim Auger to request for CSP approval, create JIRAs for Q back porting so hosting can get the fix versions Fixes to these will be included in Q-SP-5 mod-dcb-1.1.5
|
Figure out why edge APIs do not work for member tenants in intcon | By 10/03 | Done | US1315451: edge endpoint issues in the intcon cluster us-west-2 US1318659: qintcon: Param Store Entries | |||
Deploy mod-dcb-1.1.4, mod-rtac-3.6.1 to intcon | By 10/07 AM ET | Done | ||||
Deploy Q-SP-5 to MOBIUS FOLIO dry run | Done | |||||
Deploy Q-SP-5 to qintcon | By 10/17 | Done | ||||
Communicate API Keys to dcb@k-int.co.uk Send intcon keycloak creds to dcb@k-int.co.uk | By 10/18 | US1323966: qintcon - Investigate "no data" in Union Catalog - by 10/18 | ||||
Impact of FOLIO Q-SP-5 Upgrade to LOCATE | Dreamliner | By 10/22 EOD | LOCAL LOCATE DCB LOCATE(Existing catalog) In Progress |
| ||
Impact of FOLIO Q-SP-5 Upgrade to DCB(transactional / Incremental ingestion testing) | K-Int/Tim Auger | By 10/22 EOD | ||||
Testing/Sign Off for intcon(FOLIO/LOCATE/DCB) | Dreamliner/Tim/K-Int | Vijay/Tim Auger | By 10/22 EOD | |||
Full Ingestion Process | 10/22 | Before production upgrade | ||||
Test that the ingestion process worked(Full) | 10/22 | Before production upgrade | ||||
Test incremental Ingestion testing on umsystem-test against mobius-staging env | Tim Auger | Done | mod-dcb-1.1.5 were deployed to umsystem-test | |||
Upgrade MOBIUS-Staging(FOLIO) from Poppy-SP-6 to Q-SP-5 | FSE-Operations | 10/22 - 10/25 | US1316977: Q upgrades: MOBIUS Staging - Q-SP-5(10/22-10/25) | |||
Upgrade LOCATE pointing to MOBIUS-Staging to be compatible with Q | As needed | |||||
Upgrade DCB pointing to MOBIUS-staging to be compatible with Q | As needed | |||||
Testing/Sign Off for MOBIUS-Staging(FOLIO/DCB/LOCATE) | Dreamliner/K-Int/Tim Auger | By 10/30 | No full ingestion testing on Staging | |||
Buffer for any fixes/turnarounds + testing sign off | All teams | By 11/06 | ||||
umsystem prod is getting upgraded to Q-SP-5 | TBD | Postponed | Did not happen as expected on 10/09 or 10/15 - Postponed | Tim Auger, UMSystem, MCO and K-Int Switch off borrowing and supplying for umsystem - MCO | ||
UMSystem’s FOLIO Q Compatibility with DCB and communication to UMSystem in case of issue | Tim Auger to inform umsystem | 10/07 - 10/11 | Done | |||
Upgrade MOBIUS Live | FSE-Operations | Abdenour Drif/Aliaksei Luhavy | 11/15 |
|