OLE 1.0 Milestone Release Project Plan
Updated 10/21/2013
As we near completion of the 1.0 QA efforts, details of the project development are listed below.
Summary of efforts:
- QA efforts are in full force across all modules.
- First round of testing complete for Describe, Deliver, and Select & Acquire, System Integration nearly complete.
- 30 Blocker/Critical tickets remain
- 1.0 major and less pressing issues will be rolled into 1.5