endUser stories and Bugs should meet the Definition of Ready before they can be pulled into a sprint for delivery.

Table of Contents
stylenone

...

The following criteria should be met before a story is presented to the team for backlog review.

Need

...

  • User intent is explicit.

  • Business outcome is clear.

    • The story clearly articulates the value to the user, or unlocks downstream technical opportunity or reduces future product/development risk. 

  • The story has been reviewed and accepted by the usergroup. 

  • The story priority has been accepted by the usergroup.

Expectations

  • User or system roles and restrictions are defined.

  • Workflow / UI expectations or assumptions are stated.

  • Fall-back, negative and alternative scenario flows are defined in addition to core flow, including example data.

  • Related functionality or behaviour that is out of scope is explicitly defined.

  • Necessary acceptance criteria are defined and sufficiently reflect story intent and constraints, that the solution design must consider.

...

  • Do we have a shared understanding of the story?

    • We can describe the technical approach for how we're going to build the solution. Developer

    • We can describe how we haven't broken anything else by building functionality for this story. Developer

    • We know how we can demonstrate that the story meets its acceptance criteria. Developer

  • The story can be estimated, developed, tested and deployed independently of other functionality. Lead Dev

    • Incoming dependencies have been identified and resolved (either cleared or fulfilled). Lead Dev

    • The Story is linked to (requires) other tasks or stories that it is technically dependent on. Lead Dev

  • There is enough information to reasonably estimate the delivery effort. Lead Dev

    • Story Points have been captured. Scrum Master

    • Key development tasks are outlined. Lead Dev

    • There is enough information to develop a test plan. Test Lead

  • The story has been sized appropriately. Developer

    • The story is small enough to start and finish in a single iteration; ideally 1-2 days, and really less than half the sprint length. Lead Dev

When a story meets the above criteria it is ready for acceptance into the Sprint Backlog

...