OLE 1.0 Milestone Release Project PlanUpdated 7/924/2013 As we continue the 1.0 coding efforts, details of the project development are listed below. Summary of efforts: - Coding efforts continue across all modules. As they become available, SMEs are testing Jiras in the test environment.
- Acceptance criteria and test cases are nearly complete for 1.0 specifications.A code freeze is planned for mid August.
- Developers continue to make strides to absorb the deficit and make the July 31st code freeze.
- Specifications are being written and finalized for 1.5.
- Unification of the OLE screens (merging Rice2 tabs with the Main Menu and Admin tabs) is in progress.
- Modifications continue to make the OLE DocStore an RDBMS, this will improve performance of the DocStore.
Image Removed- has seen a lot of progress, efforts continue.
Image Added
|