Planned Version # | Sprint Start Date | Sprint End Date | Details | Latest Handoff DateSpecs | Milestones | Roadmap Bullet Number |
---|---|---|---|---|---|---|
4/23/2012 | 5/4/2012 | sprint1toward0.8forHTC | 4/13/2012 | |||
5/7/2012 | 5/18/2012 | sprint2toward0.8forHTC | 4/27/2012 | |||
5/21/2012 | 6/1/2012 | sprint3toward0.8forHTC | 5/11/2012 | 4.02,4.04,19.03 | ||
6/4/2012 | 6/15/2012 | sprint4toward0.8forHTC | 5/25/2012 | 2,14.02,14.03,14.06,18.07,19.01 | ||
6/18/2012 | 6/29/2012 | sprint5toward0.8forHTC | 6/8/2012 | 14.05,15.05,15.07,15.09,15.11,18.42 | ||
7/2/2012 | 7/13/2012 | sprint6toward0.8forHTC | 6/22/2012 | 4.06,13.01,13.02,13.03,18.04,18.09 | ||
7/16/2012 | 7/27/2012 | sprint7toward0.8forHTC | 7/6/2012 | 4.01,4.03,4.05,4.07,4.08,10.01,10.02,10.03,18.13,18.14 | ||
7/30/2012 | 8/10/2012 | sprint8toward0.8forHTC | 7/20/2012 | 15.03,15.08 | ||
8/13/2012 | 8/24/2012 | sprint9toward0.8forHTC | 8/3/2012 | Specification Hand off Freeze Date - 8/17/2012 |
| |
8/27/2012 | 9/7/2012 | sprint10toward0.8forHTC | 8/17/2012 | Planned Code Freeze date - 9/7/2012 |
| |
9/10/2012 | 9/21/2012 | All Defect Fixes for OLE 0.8 | ||||
9/24/2012 | 10/5/2012 | All Defect Fixes for OLE 0.8 | No further PLANNED Code Changes after 10/5/2012 |
| ||
10/8/2012 | 10/13/2012 | Setting up of Demo |
Jira Issues: Complete- Release OLE 0.8
The following is an iterative list of completed coding for OLE 0.8. Please see Jira for complete details, or Sprint Release Notes for annotated lists. Below are any coding tickets with status of "closed" for OLE 0.8.
Jira Issues | ||||||||
---|---|---|---|---|---|---|---|---|
|