Below is draft planning outline for approval. Teams, schedule and approach TBD.

I. Overview

  1. OLE requires committed SME's to complete User Documentation for all modules and all features delivered in the application. User documentation should be initiated well-before release deadlines, and in tandem with spec-writing, coding, and testing.
  2. Training, checklists, best practices will be shared across all Module SME team representatives,  and the to-be-formed User Documentation team.
  3. User Documentation should be completed within 6-12 weeks after a scheduled milestone or product release (with some variation for milestone releases, depending on FC/PM decisions for support, schedule)

...